Iraq Lucky Cement Grinding Station Contracted by TCDRI GOT FAC Certificate

Pubdate:2015-04-10

 One April 8, Iraq Lucky 2x60T/H Cement Grinding Station contracted by TCDRI obtained Final Acceptance Certificate, the effective date is March 10, 2015, indicating consummate completion of implementation works for Iraq Lucky project.

 

Iraq Lucky project was signed on June 28, 2012, and the contract period is 18 months. The project was put into production on January 16, 2014, was completed on March 12 and got PAC certificate (effective from March 10, 2014) on March 15. Project schedule complied with the requirement, and project implementation got high recognition from the Owner.

 